多层次大跨度钢梁安装技术

(整期优先)网络出版时间:2017-12-22
/ 1

多层次大跨度钢梁安装技术

魏大江郭新荣荆朝杨坤

中建钢构有限公司天津300383

摘要:本文主要针对太原某项目裙房大跨度钢梁安装过程进行阐述,本项目大跨度钢梁跨度较大,层次较多,分布在不同平面上,且大跨度钢梁位于地库上方,给施工带来较大困难,本文主要对大跨度钢梁安装思路,胎架布置,承载力计算,安装方法和特殊安装节点等方面阐述,介绍大跨度钢梁安装过程,为同类工程施工积累经验。

关键词:大跨度;多层次;胎架;承载力

TheconstructiontechnologyofMultilayerLargeandspanSteelbeam

WEIdj,GUOxinrong,JINGzhao,YANGkun

(ChinaConstructionSteelStructureCo.Ltd.Tianjin)

Abstract:Thisarticlemainlyaimsattaiyuanaprojectwithalargespansteelbeamselaboratestheinstallationprocess,theprojectislargespansteelgirderspanbigger,hierarchy,distributionindifferentplane,andthelargespansteelgirderislocatedinthebasementabove,bringstotheconstructionofthemajordifficulties,thispapermainlyforlargespansteelgirderinstallation,jigtodecorate,thebearingcapacitycalculation,installationmethodandspecialnodes,etc,introduceslarge-spansteelbeaminstallationprocess,accumulateexperienceforthesimilarengineeringconstruction.

Keywords:longspan;multi-level;Steelsupport;Thebearingcapacity

太原市某项目由2栋塔楼及裙房组成,塔楼之间主要由14根大跨度箱形钢梁及对应次梁组成,钢梁跨度为24.8m,每根钢梁重量为24t,由于塔吊吊重限制,每根钢梁分为3段。大跨度钢梁下部为地库顶板,且大跨度钢梁共3层,如采用逐层安装钢梁再进行混凝土施工会大大降低施工效率,支撑措施投入较大,且施工会受其他专业约束,不利于施工顺利进行,如何利用较少的支撑措施最有效的完成大跨度钢梁安装是施工的要点和难点。

1工程概况

该项目建筑面积228524.30㎡,地下五层,底标高为-19.1m。地上部分裙房5层,结构高度24.29米;塔楼54层,结构高度227.6m,建筑高度228.9m。本工程大跨度钢梁安装支撑措施采用某公司标准化胎架,如图1。

3.7胎架卸载与变形控制

同一立面钢梁安装完成后开始进行胎架卸载,胎架卸载由上至下进行,胎架卸载前对钢梁起拱处标高进行监测,随后开始最上方胎架卸载,卸载完成后对最上方大跨度钢梁进行标高复测,钢梁位移满足要求后开始进行下部胎架卸载,再次对钢梁标高进行复测,直至该立面胎架全部卸载完成。胎架卸载完成后用于下一立面钢梁安装,直至全部钢梁安装完成。全部胎架卸载完成后,经复测统计钢梁中间段起拱处下挠值处于8~13mm,全部满足要求。同一平面大跨度钢梁间采用次梁连接,保证钢梁侧向稳定性。

4结语

本工程大跨度钢梁安装较常规安装方式,节省了支撑措施的投入,节约工期,且减少了与其他专业的交叉施工,有效的提高了施工效率,节约施工成本。该方法利用钢梁穿胎架节点合理的解决了同一时间安装多层钢梁的问题,有效得节约了施工工期。该施工方法对同类型工程具有参考意义。

[1]周岐王亚君,焊接应力与变形的控制,辽宁科学技术出版社,2010.

[2]GB50755-2012,钢结构工程施工规范,中国建筑工业出版社,2012.

[3]GB50661-2011,钢结构焊接规范,中国建筑工业出版社,2011.

[4]中国钢结构协会,建筑钢结构施工手册,中国计划出版社,2002.